Management perspective
Concurrent delay is often treated primarily as a question of contractual entitlement. In practice, a better outcome may come from understanding the real operational impact and identifying where both parties can protect value.
The Challenge
An EPC project faced a concurrent delay: the Contractor was late delivering materials due to non-conformities, while the Client’s site was simultaneously not ready to receive them. Although no schedule impact could be attributed solely to the Contractor, the Client raised a claim of approximately €3M for delayed deliveries.
The Approach
The concurrent delay was identified early, allowing the discussion to move beyond contractual positioning and focus on commercial alignment.
The Contractor proposed that the Client withdraw the €3M claim in exchange for the Contractor assuming the actual storage costs of materials that were ready for delivery but could not yet be received on site. Coordination with suppliers also made it possible to use available free-storage periods and consolidate deliveries once the site became ready.
The Result
The Client withdrew the claim, while supplier negotiations and revised delivery planning reduced storage and logistics costs. The pragmatic solution protected cash flow, avoided a prolonged dispute and supported successful project completion despite the wider delay.
Outcome
A €3M claim was avoided, logistics exposure was contained and the Client–Contractor relationship was strengthened. More broadly, the case shows how early recognition of concurrent responsibilities can create space for a balanced solution that protects value for both parties.